An EICR is only useful if its observations become a controlled remedial programme. For a commercial property manager, that means separating immediate danger from urgent repairs, further investigation and planned improvements—then recording what was completed.

This checklist is designed for offices, managed commercial buildings, multi-site estates and other occupied premises. It does not replace the judgement of the competent person responsible for the inspection or remedial work.

Before you start: understand the EICR codes

  • C1 — danger present: make safe immediately.

  • C2 — potentially dangerous: arrange urgent remedial work.

  • C3 — improvement recommended: plan the improvement appropriately.

  • FI — further investigation required: investigate without delay so safety can be confirmed.

For a fuller explanation, read EICR Codes Explained: C1, C2, C3 and FI.

1. Confirm the report and responsibility

Before instructing work, confirm:

  • the correct property, areas and electrical installation are covered

  • the report date, inspection limitations and next recommended inspection date

  • who is responsible for authorising safety measures and remedial expenditure

  • who needs operational updates, including facilities, tenants, security and site teams

  • whether the report covers the whole installation or only an agreed sample or area

Do not assume an EICR covers emergency lighting, fire-alarm servicing, portable-appliance testing or every other compliance regime. Check the stated scope.

2. Build one prioritised action register

Transfer every C1, C2 and FI observation into a working register. Include:

  • the observation and code

  • building, floor, room, circuit or distribution-board reference

  • the immediate control already taken, if any

  • the proposed repair or investigation

  • access, isolation and operational constraints

  • responsible person, target date and current status

  • completion evidence required

Keep C3 improvements in the same register, but identify them separately so urgent items remain visible.

3. Make C1 situations safe

C1 means danger is present. The immediate priority is to remove or control the danger safely. This may require isolation or another protective measure determined by a competent electrician.

Record what was made safe, when it happened, who completed it and whether any part of the building or installation remains unavailable.

4. Scope C2 repairs and FI investigations

C2 observations require urgent remedial action. FI observations require further investigation without delay because the inspection has not established whether danger or potential danger exists.

For each item, make the contractor’s scope specific enough to price and deliver. It should identify the relevant observation, location, expected work, testing, certification and any making-good responsibility. FI work should state the question the investigation needs to answer rather than being left as an open-ended instruction.

5. Check access, isolations and business disruption

Commercial remedial work often fails at the planning stage rather than the electrical stage. Before agreeing dates, confirm:

  • normal and restricted access hours

  • tenant, security or permit requirements

  • circuits and equipment that cannot be isolated during trading hours

  • shutdown notifications and authorised decision-makers

  • sensitive rooms, IT systems, plant or business-critical loads

  • asbestos-register or building-fabric information relevant to the work area

  • whether temporary supplies or phased working need to be considered

These checks help the contractor propose a safe sequence without making unsupported assumptions about the building.

6. Review quotations against the report

A usable quotation should make it clear:

  • which EICR observations are included

  • which items need investigation before a final repair can be priced

  • what testing and certification are included

  • what access equipment, permits, isolations or attendance the client must provide

  • what is excluded

  • how completed items will be referenced back to the EICR

Avoid comparing totals alone when contractors have priced different scopes.

7. Plan C3 improvements sensibly

C3 observations do not, by themselves, make an EICR unsatisfactory. They can often be grouped with planned maintenance, refurbishment, distribution-board work or other compatible upgrades.

Keep them visible, assign a review point and record the decision. “Not urgent” should not become “forgotten.”

8. Verify completion

When work finishes, collect evidence that matches the original observation register. Depending on the work, this may include:

  • electrical certificates or test results

  • the contractor’s completion record

  • investigation findings and the resulting decision

  • updated circuit schedules or labels

  • photographs where they provide useful identification

  • confirmation that temporary controls or isolations have been removed appropriately

The person responsible for the property should be able to trace each completed item back to the original EICR observation.

9. Close out the remedial programme

Before marking the programme complete:

  • confirm every C1, C2 and FI item has a recorded outcome

  • record any additional defects found during investigation or repair

  • update the action register and compliance records

  • communicate residual restrictions or planned C3 work

  • retain the report, certificates and supporting evidence together

  • diarise the next inspection or relevant review date from the competent person’s recommendation

Do not describe the original report as satisfactory unless the appropriate competent person has provided the evidence or confirmation needed to support that conclusion.

EICR remedial works checklist summary

  • Confirm the report scope and responsible people

  • Register every C1, C2, C3 and FI observation

  • Make C1 danger safe immediately

  • Scope urgent C2 repairs

  • Define and complete FI investigations without delay

  • Confirm access, isolations and operational constraints

  • Check quotations cover the same observations and evidence

  • Plan and review C3 improvements

  • Collect certificates, findings and completion records

  • Close every urgent item and update the compliance file

Need help turning an EICR into a remedial plan?

Azure Electrical supports commercial electrical compliance and remedial planning from Ashford across Kent, with suitable project-led work in London. Contact Azure Electrical and provide the EICR where possible so the team can review the codes, locations and access requirements before discussing the next step.